How a skid built in China passes inspection in the United States and Canada: which code governs each component, who applies the nameplate and stamp, how CRN registration works, how control panels are certified, and which records you receive.
Established: 2011 Jiangsu workshop: 17,000 m² Pressure codes: VIII · B31.3 · IX Before shipment: FAT, every skid
Which codes apply to each part of a Rockerhill process skid?
SHORT ANSWER On a Rockerhill skid, pressure vessels follow ASME BPVC Section VIII Division 1, interconnecting process piping follows ASME B31.3, and every pressure weld is made to procedures and welders qualified under ASME BPVC Section IX. Control panels are specified to UL 508A for the United States or CSA C22.2 No. 286 for Canada.
A process skid is not certified as one item. Each component has its own code and its own proof of compliance, and an inspector checks them one by one. The table shows what governs each part and which record proves it.
Code map for a typical Rockerhill process skid
|
Component |
Governing code |
Mark or proof |
Responsible party |
Record in your data book |
|
Pressure vessels (separators, scrubbers, buffer tanks, receivers) |
ASME BPVC Section VIII, Div. 1 |
ASME Certification Mark with U designator; National Board registration where the jurisdiction requires it |
ASME Certificate holder, with an Authorized Inspector |
Form U-1 or U-1A, material test reports, NDE reports, hydrotest record, nameplate photo |
|
Shell-and-tube heat exchangers |
Section VIII, Div. 1, plus TEMA class if specified |
U designator |
ASME Certificate holder, with an Authorized Inspector |
Form U-1, TEMA datasheet, tube test records |
|
Process piping on the skid |
ASME B31.3 |
No code stamp. Compliance is shown by records |
Fabricator; verified by the owner's Inspector |
Isometrics, weld map, NDE records, leak test record |
|
Pressure welding |
ASME BPVC Section IX |
Qualified WPS, PQR and welder qualifications |
Fabricator |
WPS/PQR index, welder qualification records, weld log |
|
Valves, flanges and fittings |
ASME B16.5, B16.34 and related standards |
Manufacturer marking; CRN for fittings in Canada |
Component manufacturer |
Material certificates, fitting CRN list |
|
Pressure relief valves |
Section VIII overpressure protection rules |
ASME UV designator and certified capacity |
Valve manufacturer |
Valve datasheet, set pressure certificate |
|
Industrial control panel |
UL 508A (US) or CSA C22.2 No. 286 (Canada) |
UL 508A label, cUL, CSA mark, or a field evaluation label |
TUV or BV, or SGS |
Wiring diagrams, SCCR calculation, label record |
|
Skid frame and lifting points |
AISC 360 or the project's structural standard |
Engineering calculation |
Skid designer |
Structural and lifting calculations |
Rockerhill agrees the code edition, stamping route and third-party inspection arrangement with each client in writing before design starts.
Who applies the ASME nameplate and stamp on a Rockerhill skid?
SHORT ANSWER Only a holder of an ASME Certificate of Authorization can apply the U mark, and only after an Authorized Inspector accepts the vessel. A skid builder either holds that certificate or buys stamped vessels from a certificate holder. B31.3 piping carries no stamp. Rockerhill states which route applies in the code basis letter for each project.
A third-party inspection company cannot replace an ASME Authorized Inspector, and a fabricator without a certificate cannot stamp a vessel even if every weld was inspected. That leaves three real routes.
Three stamping routes for vessels on an imported skid
|
Route |
Who applies the U mark |
Who inspects |
What you receive |
Fits when |
Watch for |
|
A. Skid builder holds an ASME U Certificate |
Skid builder |
Authorized Inspector from the builder's Authorized Inspection Agency |
Form U-1 signed by the Authorized Inspector; National Board registration if ordered |
Stamped vessels are required and you want one party responsible |
Check certificate scope and expiry in ASME's certificate holder directory |
|
B. Stamped vessels bought from a certified vessel shop |
Vessel manufacturer |
That manufacturer's Authorized Inspector |
Vessel maker's Form U-1; skid builder supplies B31.3 piping records |
The skid builder has no U Certificate |
Vessel lead time and clear interface responsibility |
|
C. Designed to ASME, not stamped |
No one |
Third-party inspection body |
Inspection certificate and record book, but no U mark |
The owner and jurisdiction accept unstamped vessels |
Most US states and Canadian provinces require stamped or registered vessels, so this route usually fails there |
How is CRN registration handled for skids going to Canada?
SHORT ANSWER In Canada, pressure vessel and fitting designs must be registered with the provincial safety authority under CSA B51 and receive a Canadian Registration Number (CRN) before installation. Rockerhill lists the registrable items at proposal stage so registration runs alongside engineering, not after fabrication, when a rejected design means rework.
1. Confirm the province. Registration is provincial. A CRN issued in one province can be extended to others, but each one reviews separately.
2. List every registrable item. Vessels, heat exchangers and fittings such as valves, strainers and expansion joints. Check which bought-in fittings already hold a CRN for that province. Some provinces also register the piping system.
3. Confirm the quality program. The authority must accept the manufacturer's quality program. An ASME Certificate of Authorization is the usual evidence.
4. Submit the design. Drawings, code calculations, material specifications and design conditions go to the authority. Reviewer comments are answered before fabrication is released.
5. Receive the CRN. The number is added to the nameplate and the data report.
6. Fabricate and inspect. The final data book lists the CRN for each vessel and fitting.
Provincial authorities that issue CRNs (selection)
|
Province |
Authority |
|
Alberta |
ABSA, the pressure equipment safety authority |
|
Ontario |
Technical Standards and Safety Authority (TSSA) |
|
British Columbia |
Technical Safety BC |
|
Saskatchewan |
Technical Safety Authority of Saskatchewan (TSASK) |
|
Québec |
Régie du bâtiment du Québec (RBQ) |
Rockerhill's Canadian reference is a CO2 direct air capture balance-of-plant skid, awarded in May 2026, that includes custom heat exchangers, vacuum scrubbers and a dry screw compressor. And Rockerhill provided CRN registration as part of service scope.
How do Rockerhill control panels meet UL 508A or CSA requirements?
SHORT ANSWER North American electrical inspectors look for a certification mark on the complete industrial control panel, not only on its parts. A panel can be labeled by a UL 508A listed shop, certified to CSA C22.2 No. 286, or field evaluated on site. Rockerhill agrees the route with the client before panel design starts.
Certification routes for skid control panels
|
Route |
Mark on the panel |
Accepted in |
Notes |
|
UL 508A listed panel shop |
UL 508A label; cUL when Canadian requirements are included |
United States; Canada with cUL |
The shop itself must be listed. Components must be UL listed or recognized, and the panel must be marked with its short-circuit current rating (SCCR) |
|
CSA certified panel |
CSA mark (C22.2 No. 286) |
Canada; United States with the CSA-US mark |
Same principle: certified design, certified components, marked ratings |
|
Field evaluation |
Field evaluation label from an accredited body |
Case by case, at site |
Done after delivery. Any finding becomes site rework, so it is the fallback route |
Rockerhill builds panels in the same workshop as the piping, using drives and controls from suppliers such as ABB and Allen-Bradley, with PLC, HMI and communication protocol chosen by the client.
Which compliance documents do you receive, and can you see samples?
SHORT ANSWER Every Rockerhill skid ships with a data book covering materials, welding, examination and testing. Before you order, you can review three anonymized samples: a Manufacturer's Data Report, a WPS/PQR index and an Inspection and Test Plan. Your inspector can check our format and hold points before a purchase order is placed.
Manufacturer's Data Report (MDR)
Form U-1 or U-1A layout, serial and National Board numbers masked
Design conditions: MAWP, MDMT, design temperature, corrosion allowance, joint efficiency
Material list with SA specification, grade and masked heat numbers
Hydrostatic test pressure and date
Certificate holder and Authorized Inspector signature blocks (redacted)
Attached nameplate photo, MTRs, NDE and PWHT records
WPS/PQR index
WPS number and process (GTAW, SMAW, GTAW + SMAW)
Base metal P-numbers covered, such as carbon steel, 304/316L and duplex
Filler F-number and A-number
Thickness range and positions qualified
PWHT and impact test status
Supporting PQR number for each WPS, plus welder continuity summary
Inspection and Test Plan (ITP)
Each step from material receipt to packing
Reference document and acceptance criteria for each step
Record produced at each step
Hold, witness and review points for Rockerhill QC, third-party inspector, Authorized Inspector and client
FAT procedure and punch-list close-out
Rockerhill keeps material and welding records for every pressure part, so the documentation package follows the equipment to site. Please contact us if you want any document samples.
How is compliance checked before a Rockerhill skid ships?
SHORT ANSWER Compliance is checked at fixed points from the code basis letter to the final data book: design review, material receipt, welding, examination, pressure testing, electrical checks and a witnessed factory acceptance test. Each point produces a record, so an inspector on site can trace any weld or plate back to its certificate.
1. Code basis letter. Code edition, stamping route, inspection parties, CRN and panel certification agreed in writing.
2. Design review. P&ID, general arrangement, 3D layout and vessel calculations reviewed with the client before fabrication.
3. Material receipt. Material test reports checked against the specification, with heat numbers transferred to each part.
4. Welding. Only qualified WPSs and qualified welders, recorded on a weld map.
5. Examination. Radiography, ultrasonic, magnetic particle or penetrant testing as the code and the order require.
6. Pressure testing. Vessels are hydrotested at the Section VIII test pressure, normally 1.3 times MAWP adjusted for temperature. Piping is leak tested to B31.3, normally 1.5 times design pressure.
7. Electrical and loop checks. Wiring, insulation and instrument loops checked, then alarms and interlocks tested.
8. Factory acceptance test. Functional run witnessed by the client in person or by video, with a punch list closed before shipment.
9. Data book handover. MDRs, piping records, weld and NDE records, test reports and certificates delivered with the skid.
Rockerhill performs a factory acceptance test on every skid at its 17,000 m² Jiangsu facility before shipment, and clients can witness it in person or by video.
Frequently asked questions
Is a process skid "ASME certified"?
No skid is certified as a whole. Individual vessels carry the ASME U mark, and piping complies with B31.3 through its records. Ask which vessels are stamped and by whom.
Can a manufacturer in China hold an ASME U Certificate?
Yes. ASME issues certificates to manufacturers worldwide, and many Chinese vessel shops hold them. You can verify any certificate in ASME's online certificate holder directory.
Does B31.3 piping need a third-party inspector?
B31.3 requires the owner's Inspector to verify that examination and testing were done. The owner chooses who that is, often a third-party inspection company.
Do vessels shipped to the US need National Board registration?
Many US states require National Board registration of stamped vessels. Confirm the requirement for the installation state before ordering.
Send your P&ID and installation location
Tell us the state or province where the skid will be installed. Rockerhill, founded in 2011 with its head office in Beijing, returns a code basis letter with the proposal that lists the codes, stamping route, registrations and documents for your project.
Allie.s@rockerhillcn.com · +86 157 5752 3989 · www.rockerhillcn.com