Bar Screen Head Loss Calculation: How To Size A Screen Channel

Nov 19, 2026

Leave a message

Bar screen head loss is the drop in water level across a screen, caused by the bars themselves and by the screenings trapped on them. It sets how deep the upstream channel must be, how high the walls and overflow must sit, and when the rakes should start. Get it wrong and the channel overtops in a storm, or the upstream sewer surcharges, or grit settles in a channel that is too slow.

Most guides stop at "keep the velocity between 0.6 and 1.0 m/s." This article goes further. It shows the two equations engineers actually use, works a full example from flow to channel width, and shows why a screen that loses 40 mm clean can lose more than 250 mm half-blinded. The method is the one ROCKERHILL engineers use when we size multi-rake bar screens, band screens and fine screens for headworks, pumping stations and intakes.

The three velocities that matter

Before any head loss calculation, check three velocities. Each one protects against a different failure.

Velocity

Where it is measured

Typical design range

What goes wrong outside the range

Approach velocity (v)

In the channel just upstream of the screen

At least 0.4 m/s at average flow; up to about 0.9 m/s at peak

Too low: grit and sand settle in front of the rack. Too high: debris is forced through and head loss rises

Through-bar velocity (V)

Through the clear openings between bars

0.6 to 1.0 m/s at peak flow for mechanically cleaned screens

Too high: rags and soft solids are pushed through the openings, and head loss climbs with the square of velocity

Through-screen velocity (fine screens and intakes)

Through the open area of mesh or perforated panels

Set by opening size and duty; often 0.15 m/s or less where fish protection rules apply

Impingement of fish, high head loss, fast blinding

These are general design figures found in standard wastewater references such as Metcalf & Eddy. Local design standards and client specifications take precedence.

The two head loss equations

1. Kirschmer equation (clean bar rack)

The Kirschmer equation estimates head loss through a clean rack from the bar shape, bar thickness and clear spacing:

h = β × (w / b)^(4/3) × (v² / 2g) × sin θ

Symbol

Meaning

h

Head loss (m)

β

Bar shape factor (see table)

w

Bar thickness facing the flow (mm)

b

Clear spacing between bars (mm)

v

Approach velocity upstream of the rack (m/s)

g

9.81 m/s²

θ

Rack angle from horizontal

Bar shape

Shape factor β

Sharp-edged rectangular

2.42

Rectangular with semicircular upstream face

1.83

Circular

1.79

Rectangular with semicircular upstream and downstream faces

1.67

Teardrop (streamlined)

0.76

The table shows something many buyers miss: bar profile matters. A teardrop bar has roughly a third of the clean head loss of a flat rectangular bar with the same thickness and spacing. Profiled bars cost more but can let you choose a narrower spacing without deepening the channel.

2. Orifice equation (clean and partly blinded screen)

Kirschmer only describes a clean rack. In operation, the rack is always partly covered with screenings, so designers also use the orifice form of the energy equation:

h = (1 / C) × (V² − v²) / 2g

Symbol

Meaning

V

Velocity through the clear openings (m/s)

v

Approach velocity (m/s)

C

Empirical discharge coefficient: about 0.7 for a clean screen and 0.6 for a clogged screen

To model blinding, reduce the clear area. If the rack is 30% blinded, only 70% of the clear openings pass flow, so V rises by a factor of 1 / 0.7.

For mesh and perforated plate fine screens

For fine screens, band screens and drum screens, use the open area of the screening media:

h = (1 / 2g) × (Q / (C × A))²

where Q is the flow (m³/s), A is the effective submerged open area of the media (m²) and C is about 0.6 for a clean screen. The manufacturer should state the open area of the mesh or plate, because it varies widely between products with the same nominal opening.

Worked example: sizing a 10 mm multi-rake bar screen channel

Design data (illustrative):

Input

Value

Peak flow, Q

0.5 m³/s (43,200 m³/day)

Water depth upstream of the screen at peak flow

1.0 m

Clear bar spacing, b

10 mm

Bar thickness, w

8 mm, sharp-edged rectangular

Rack angle, θ

75°

Target through-bar velocity at peak, V

≤ 0.9 m/s

Step 1: Required clear area

Clear area needed = Q / V = 0.5 / 0.9 = 0.556 m²

Step 2: Required clear width

Using the vertical water depth (a conservative simplification, because the inclined rack is slightly longer than the depth):

Clear width = 0.556 m² / 1.0 m = 0.556 m

Step 3: Channel width

Open-area ratio of the rack = b / (b + w) = 10 / 18 = 0.556

Channel width = clear width / open-area ratio = 0.556 / 0.556 = 1.0 m

Step 4: Check approach velocity

v = Q / (channel width × depth) = 0.5 / (1.0 × 1.0) = 0.5 m/s

This is above 0.4 m/s, so grit should stay moving at peak flow. Check again at average and minimum flows. If velocity falls well below 0.4 m/s at night, consider a narrower duty channel with a standby channel, or a channel invert profile that keeps velocity up.

Step 5: Clean head loss

Kirschmer: h = 2.42 × (8/10)^(4/3) × (0.5² / 19.62) × sin 75° = 0.022 m (22 mm)

Orifice equation, C = 0.7: h = (1 / 0.7) × (0.9² − 0.5²) / 19.62 = 0.041 m (41 mm)

The two methods differ because they make different assumptions. Use the higher figure for design, and treat both as the clean starting point only.

Step 6: Head loss as the rack blinds

Rack condition

Through-bar velocity V

C

Head loss

Clean

0.90 m/s

0.7

41 mm

30% blinded

1.29 m/s

0.6

119 mm

50% blinded

1.80 m/s

0.6

254 mm

70% blinded

3.00 m/s

0.6

743 mm

These figures hold the upstream depth constant. In reality the upstream level rises as head loss grows, which lowers the velocities slightly, so a full design iterates. The trend is what matters.

The lesson: head loss rises with the square of velocity. Going from 30% to 50% blinding roughly doubles it, and a rack left to reach 70% blinding loses three-quarters of a metre. This is why cleaning frequency, not just bar spacing, controls the hydraulic design.

Turning the numbers into a channel design

Set the rake control points. Start the rakes on a differential level well before the head loss becomes a hydraulic problem. In the example, a start point around 50 to 100 mm and a high-speed or alarm point around 150 to 250 mm would keep the screen in its comfortable range. The final values depend on the upstream sewer and the downstream channel.

Design the channel walls for the blinded case. Wall height = downstream peak level + maximum design head loss + freeboard. Many specifications set the maximum design head loss for a mechanically cleaned screen somewhere between 150 and 600 mm.

Set the overflow or bypass. An emergency overflow weir or a bypass channel with a manual bar rack should operate before the upstream sewer surcharges, not after.

Check the upstream sewer. On a retrofit, a narrower bar spacing adds head loss. Make sure the higher upstream level does not back up into the incoming sewer at peak flow.

Check every flow case. Repeat the calculation at minimum, average and peak flow, and with one channel out of service if you have duty and standby screens.

How ROCKERHILL sizes a screen

For every enquiry, ROCKERHILL engineers run this calculation from the client's flow data and channel drawing before we propose a screen. We then fit the screen to the channel, not the other way round: our multi-rake bar screens are built for channels up to 4,800 mm wide and about 7.3 m deep, with bar spacing from 3 to 50 mm and a choice of bar profiles. The vendor data sheet states the clean and dirty head loss at peak flow, the rake speed and the control set points, so the civil designer has the numbers needed for the channel. On one industrial seawater intake data sheet, for example, the head loss was specified at ≤ 0.25 m clean and dirty at a peak flow of 3,000 m³/h with 30 mm bar spacing.

Design, engineering and in-house manufacturing

A head loss calculation is only useful if the screen that is built matches it. At ROCKERHILL the same engineering team that runs the hydraulic check also designs, builds and tests the screen, so the numbers on the data sheet are the numbers you get in the channel.

Capability

What it means for your project

In-house design and engineering

Our own engineers size the rack, chains, rakes, panels and frame by calculation from your flow, channel geometry, discharge height and water chemistry. We check the hydraulics before we propose a screen.

Customisation

Every screen is built to the channel: widths up to 4,800 mm and depths of about 7.3 m delivered, bar spacing from 3 to 50 mm, a choice of bar profiles and mesh or perforated plate panels, AISI 304, 316L, duplex 2205 or coated carbon steel, and drives for the local power supply.

Project documentation

General arrangement drawings, vendor data sheets, structural calculations, ITPs, O&M manuals and spare parts lists, in the client's format and revision system, issued for approval before fabrication.

Codes and standards

Design to ASTM, ASME, EN and GB codes or to the project specification; welding to ASME Section IX procedures; EN 10204 3.1 material certificates.

In-house manufacturing

Cutting, welding, machining, and pickling and passivation of stainless steel in our own workshops in China, under our own quality control, with visual and penetrant inspection of welds.

Factory testing

Every screen is fully assembled and function-tested before shipment, witnessed by the client or recorded on photo and video. Third-party inspection is accepted.

Delivery and support

Export packing on flat racks or in bolted modules for wide units, installation drawings, remote commissioning support and site supervision on request.

One supplier for the package

Screens, screenings handling equipment, and the penstocks, sluice gates, stoplogs and radial gates that isolate screen channels, from one engineering team.

One team owns each project, from the first sizing calculation to the last commissioning check.

Global project references

ROCKERHILL screens are sized this way for municipal, industrial and intake projects around the world. ROCKERHILL has project references in 30 countries, and our bar screens and related screening equipment are in service across the United States, Canada, Australia and Singapore, as well as Mexico, Croatia, the Middle East and China.

Project

Scope

Location

PPLAK project

4 sets of AISI 316L stainless steel bar screens for a coastal, high-chloride environment

Singapore

Aquatech project

Cooling water intake screen, with stoplogs and radial gates for the same plant

Mexico

National Water Administration

Bar screen and band screen, with penstocks, for public water infrastructure

Croatia

Nancun waterworks inlet well, South-to-North Water Diversion

GQ-B multi-rake bar screen for a 4,800 mm wide channel, 7,347 mm deep

Shijiazhuang, China

Beyond screening, ROCKERHILL's engineering and fabrication references in North America and Asia-Pacific include an ASME-coded CO₂ carbon capture process skid for Canada, an H₂O₂ production skid for the USA, fish gates for a fish passage project in Australia and radial and sluice gates for projects in Mexico, Croatia, Singapore and the Middle East. The full reference list is available on request.

Frequently asked questions

How do you calculate head loss through a bar screen? For a clean rack, use the Kirschmer equation, h = β (w/b)^(4/3) (v²/2g) sin θ. For a partly blinded rack, use the orifice equation, h = (1/C)(V² − v²)/2g, with C about 0.7 clean and 0.6 clogged.

What is the recommended velocity through a bar screen? For mechanically cleaned screens, the velocity through the clear openings is usually kept between 0.6 and 1.0 m/s at peak flow, with an approach velocity of at least 0.4 m/s to prevent grit settling.

What is a typical head loss for a mechanical bar screen? A clean mechanical bar screen typically loses a few tens of millimetres. Channels are usually designed for a maximum head loss of 150 to 600 mm with the rack partly blinded.

What blinding percentage should I use for design? Many designers use 30 to 50% blinding for the design case. The right figure depends on the debris load and on how often the rakes clean the rack.

What is the Kirschmer shape factor for a rectangular bar? 2.42 for a sharp-edged rectangular bar, 1.83 for a rectangular bar with a rounded upstream face and 0.76 for a teardrop bar.

Why is my screen head loss higher than the design value? Usually because the rack is more blinded than assumed: rakes run too seldom, the level sensors are fouled, or the debris load is higher than expected.

How wide should a bar screen channel be? Divide the peak flow by the target through-bar velocity and the water depth to get the clear width, then divide by the open-area ratio b/(b + w). Then check that the approach velocity stays at or above 0.4 m/s.

Where has ROCKERHILL supplied screens? ROCKERHILL bar screens and related screening equipment are in service in the United States, Canada, Australia and Singapore, as well as Mexico, Croatia, the Middle East and China, among project references in 30 countries.

Does ROCKERHILL design and manufacture its screens in house? Yes. Our own engineers design every screen, it is fabricated in our own workshops in China, and it is fully assembled and tested in the factory before shipment.


Need a second opinion on a screen channel? Send your flow data and channel drawing to ROCKERHILL, and our engineers will return a head loss check and a sized screen proposal. Contact Allie at Allie.s@rockerhillcn.com.

Author: [Allie Shen], ROCKERHILL. Last updated: [Nov 17,2026].

Send Inquiry