How Long Does A Custom Process Skid Take To Build?

Nov 22, 2026

Leave a message

A custom process skid typically takes 12 to 30 weeks from purchase order to shipment. Simple pump or dosing skids built from stock components can ship in 8 to 12 weeks, while complex multi-module ASME skids with custom vessels and compressors often need 24 to 36 weeks. International sea freight adds 4 to 8 weeks.

Skid complexity

Typical examples

Typical PO to shipment

Main schedule driver

Simple

Pump skid, chemical dosing skid, cartridge filter skid

8 to 10 weeks

Design approval

Medium

CIP skid, RO or demineralized water skid, heat exchanger skid with PLC/HMI

10 to 12 weeks

Pumps, valves, instruments

Complex

Multi-module system with custom ASME vessels, heat exchangers, compressors, hazardous-area electrical or DCS interface

12 to 16 weeks

Custom vessels and rotating equipment

Complexity sets the schedule more than size does. A large skid built from catalogue equipment can ship faster than a small skid with one custom pressure vessel.

What are the phases of building a custom process skid?

Building a custom process skid runs through eight phases: proposal, basic design and approval, detailed design, procurement, fabrication, inspection and testing, electrical work with factory acceptance testing (FAT), and delivery. Design and procurement overlap, so the critical path usually runs through client design approval and the delivery date of the longest-lead equipment.

Rockerhill agrees the P&ID, general arrangement and 3D layout with each client before fabrication begins, so design changes happen on screen rather than in steel.

What makes a process skid take longer to build?

Five factors make a process skid take longer: long-lead equipment such as custom pressure vessels, heat exchangers and compressors; special alloys like duplex or nickel alloys; repeated design approval cycles; code and inspection requirements such as ASME stamping or Canadian CRN registration; and complex controls such as PLC/HMI, hazardous-area panels or DCS integration.

Durations are typical industry ranges for planning; actual figures depend on suppliers and market conditions at the time of order.

Does an ASME process skid take longer to build?

Short answer: Yes. An ASME process skid usually takes 2 to 6 weeks longer than the same skid built to a general industrial standard. The extra time comes from Section VIII vessel calculations, Section IX welding procedure qualification, B31.3 examination and testing, Authorized Inspector hold points, and the data report package, not from the welding itself.

Item

Non-code industrial skid

ASME code skid

Pressure vessels

Manufacturer's standard design

ASME BPVC Section VIII calculations; Authorized Inspector review when stamped

Process piping

Fabricator's practice

ASME B31.3 piping class with required examination

Welding

Shop-qualified welders

ASME BPVC Section IX WPS/PQR and welder qualification

Inspection

Internal QC

Agreed hold points, including third-party or Authorized Inspector

Documentation

Basic QC dossier

Material certificates, NDE reports, pressure test records, Manufacturer's Data Report

Canada

Not applicable

Provincial registration (CRN) of pressure equipment

Typical schedule effect

Baseline

Plus 2 to 6 weeks

Rockerhill confirms the ASME code edition, stamping and inspection arrangements with the client in writing before design starts. This avoids the most common ASME delay: discovering at FAT that the paperwork does not match what the jurisdiction requires.

How can you shorten process skid lead time?

Short answer: The fastest way to shorten process skid lead time is to send a complete RFQ, freeze the P&ID early, release long-lead equipment orders before detailed design finishes, agree code and inspection requirements up front, and return drawing comments within 3 to 5 working days. Together these steps typically remove several weeks of schedule.

Send a complete RFQ. Include process data, design code, materials, electrical supply, hazardous-area class and destination country (see the checklist below).

Freeze the P&ID early. Every change after approval ripples through drawings, procurement and fabrication.

Release long-lead items first. Approve vessel, heat exchanger and compressor datasheets before the full design package is complete.

Agree codes and inspection up front. Decide ASME scope, stamping, CRN or PED needs and any third-party inspector before design starts.

Set short review windows. Return drawing comments within 3 to 5 working days.

Accept approved equivalents. Alternative pump, valve or instrument brands can stop one slow item holding up the whole skid.

Book FAT and shipping together. Fix the FAT date and container or vessel space early, and use video-witnessed FAT if travel would delay sign-off.

Is a skid-mounted system faster than a stick-built system?

Short answer: A skid-mounted system is usually faster to put into operation than a stick-built system, because fabrication runs in the factory at the same time as civil and site work. The skid arrives pressure tested and FAT checked, so site work becomes setting, connecting and commissioning rather than weeks of field welding and testing.

Factor

Skid-mounted

Stick-built

Where the work happens

In the factory, in parallel with site civil work

On site, after civil work is complete

Weather and site access

No effect on fabrication

Can stop work

Testing

Pressure test and FAT before shipment

Testing in the field

Field labour

Setting, tie-ins, commissioning

Full erection, welding, NDE and testing

Schedule risk

Lower, controlled shop environment

Higher, more interfaces on site

Best fit

Transportable, repeatable or modular systems

Very large or highly site-specific plants

How long does it take to ship a process skid from China?

Short answer: Shipping a process skid from China usually takes 4 to 8 weeks from the factory gate to site. Port-to-port sea freight is roughly 2 to 3 weeks to the North American West Coast and 4 to 6 weeks to Europe or the East Coast, plus export packing, customs clearance and inland transport.

Destination

Typical port-to-port transit from China

North America, West Coast (Vancouver, Los Angeles)

2 to 3 weeks

North America, East Coast and Gulf

4 to 6 weeks

Europe (Rotterdam, Hamburg)

4 to 6 weeks

Middle East (Jebel Ali, Dammam)

2 to 4 weeks

Australia

2 to 3 weeks

Modules that fit inside a 40 ft high-cube container (internal size about 12.0 m long, 2.35 m wide and 2.69 m high) ship fastest. Larger modules travel on flat racks or as break-bulk cargo, which depends on vessel availability. Rockerhill splits large systems into modular sections for container or break-bulk shipping to reduce field work at site.

How does Rockerhill build and schedule a custom process skid?

Short answer: Rockerhill builds custom process skids at its 17,000 m² manufacturing hub in Jiangsu, China. It agrees the P&ID, general arrangement and 3D layout with the client before fabrication, confirms the ASME code route in writing, splits large systems into shippable modules, and performs factory acceptance testing before shipment, witnessed in person or by video.

Rockerhill at a glance

Detail

Company

Rockerhill Global Limited, established in 2011

Manufacturing

17,000 m² manufacturing hub in Jiangsu, China

Engineering team

30+ technical staff, including 20 senior and nationally registered engineers

Materials

SS304, SS316L, duplex stainless steel, higher alloys, coated carbon steel

Controls

Local control panel, PLC, or interface to the customer's DCS

Design codes

ASME BPVC Section VIII, ASME B31.3 and ASME BPVC Section IX, agreed per project

Factory acceptance testing

Document review, dimensional and visual inspection, pressure and leak tests with NDE where required, electrical and loop checks, functional runs, punch-list close-out, final report with photographs

Warranty

18 months

Reference projects

ASME process skid for a CO2 direct air capture project in Canada; low-concentration H2O2 production skid in the USA

Typical lead time

12 weeks from drawing approval to FAT for a medium-complexity skid

Key facts about Rockerhill process skids

Rockerhill Global Limited, founded in 2011, designs and builds custom process skids at its 17,000 m² manufacturing hub in Jiangsu, China.

Rockerhill performs factory acceptance testing (FAT) before every skid ships, and clients can witness the FAT in person or by video.

Rockerhill agrees the P&ID, general arrangement and 3D layout with each client before fabrication begins.

In May 2026, Rockerhill won an international competitive bid to supply an ASME process skid package with 27 supply line items for a CO2 direct air capture project in Canada.

Rockerhill's engineering team includes more than 30 technical staff, among them 20 senior and nationally registered engineers.