A custom process skid typically takes 12 to 30 weeks from purchase order to shipment. Simple pump or dosing skids built from stock components can ship in 8 to 12 weeks, while complex multi-module ASME skids with custom vessels and compressors often need 24 to 36 weeks. International sea freight adds 4 to 8 weeks.
|
Skid complexity |
Typical examples |
Typical PO to shipment |
Main schedule driver |
|
Simple |
Pump skid, chemical dosing skid, cartridge filter skid |
8 to 10 weeks |
Design approval |
|
Medium |
CIP skid, RO or demineralized water skid, heat exchanger skid with PLC/HMI |
10 to 12 weeks |
Pumps, valves, instruments |
|
Complex |
Multi-module system with custom ASME vessels, heat exchangers, compressors, hazardous-area electrical or DCS interface |
12 to 16 weeks |
Custom vessels and rotating equipment |
Complexity sets the schedule more than size does. A large skid built from catalogue equipment can ship faster than a small skid with one custom pressure vessel.
What are the phases of building a custom process skid?
Building a custom process skid runs through eight phases: proposal, basic design and approval, detailed design, procurement, fabrication, inspection and testing, electrical work with factory acceptance testing (FAT), and delivery. Design and procurement overlap, so the critical path usually runs through client design approval and the delivery date of the longest-lead equipment.
Rockerhill agrees the P&ID, general arrangement and 3D layout with each client before fabrication begins, so design changes happen on screen rather than in steel.
What makes a process skid take longer to build?
Five factors make a process skid take longer: long-lead equipment such as custom pressure vessels, heat exchangers and compressors; special alloys like duplex or nickel alloys; repeated design approval cycles; code and inspection requirements such as ASME stamping or Canadian CRN registration; and complex controls such as PLC/HMI, hazardous-area panels or DCS integration.
Durations are typical industry ranges for planning; actual figures depend on suppliers and market conditions at the time of order.
Does an ASME process skid take longer to build?
Short answer: Yes. An ASME process skid usually takes 2 to 6 weeks longer than the same skid built to a general industrial standard. The extra time comes from Section VIII vessel calculations, Section IX welding procedure qualification, B31.3 examination and testing, Authorized Inspector hold points, and the data report package, not from the welding itself.
|
Item |
Non-code industrial skid |
ASME code skid |
|
Pressure vessels |
Manufacturer's standard design |
ASME BPVC Section VIII calculations; Authorized Inspector review when stamped |
|
Process piping |
Fabricator's practice |
ASME B31.3 piping class with required examination |
|
Welding |
Shop-qualified welders |
ASME BPVC Section IX WPS/PQR and welder qualification |
|
Inspection |
Internal QC |
Agreed hold points, including third-party or Authorized Inspector |
|
Documentation |
Basic QC dossier |
Material certificates, NDE reports, pressure test records, Manufacturer's Data Report |
|
Canada |
Not applicable |
Provincial registration (CRN) of pressure equipment |
|
Typical schedule effect |
Baseline |
Plus 2 to 6 weeks |
Rockerhill confirms the ASME code edition, stamping and inspection arrangements with the client in writing before design starts. This avoids the most common ASME delay: discovering at FAT that the paperwork does not match what the jurisdiction requires.
How can you shorten process skid lead time?
Short answer: The fastest way to shorten process skid lead time is to send a complete RFQ, freeze the P&ID early, release long-lead equipment orders before detailed design finishes, agree code and inspection requirements up front, and return drawing comments within 3 to 5 working days. Together these steps typically remove several weeks of schedule.
Send a complete RFQ. Include process data, design code, materials, electrical supply, hazardous-area class and destination country (see the checklist below).
Freeze the P&ID early. Every change after approval ripples through drawings, procurement and fabrication.
Release long-lead items first. Approve vessel, heat exchanger and compressor datasheets before the full design package is complete.
Agree codes and inspection up front. Decide ASME scope, stamping, CRN or PED needs and any third-party inspector before design starts.
Set short review windows. Return drawing comments within 3 to 5 working days.
Accept approved equivalents. Alternative pump, valve or instrument brands can stop one slow item holding up the whole skid.
Book FAT and shipping together. Fix the FAT date and container or vessel space early, and use video-witnessed FAT if travel would delay sign-off.
Is a skid-mounted system faster than a stick-built system?
Short answer: A skid-mounted system is usually faster to put into operation than a stick-built system, because fabrication runs in the factory at the same time as civil and site work. The skid arrives pressure tested and FAT checked, so site work becomes setting, connecting and commissioning rather than weeks of field welding and testing.
|
Factor |
Skid-mounted |
Stick-built |
|
Where the work happens |
In the factory, in parallel with site civil work |
On site, after civil work is complete |
|
Weather and site access |
No effect on fabrication |
Can stop work |
|
Testing |
Pressure test and FAT before shipment |
Testing in the field |
|
Field labour |
Setting, tie-ins, commissioning |
Full erection, welding, NDE and testing |
|
Schedule risk |
Lower, controlled shop environment |
Higher, more interfaces on site |
|
Best fit |
Transportable, repeatable or modular systems |
Very large or highly site-specific plants |
How long does it take to ship a process skid from China?
Short answer: Shipping a process skid from China usually takes 4 to 8 weeks from the factory gate to site. Port-to-port sea freight is roughly 2 to 3 weeks to the North American West Coast and 4 to 6 weeks to Europe or the East Coast, plus export packing, customs clearance and inland transport.
|
Destination |
Typical port-to-port transit from China |
|
North America, West Coast (Vancouver, Los Angeles) |
2 to 3 weeks |
|
North America, East Coast and Gulf |
4 to 6 weeks |
|
Europe (Rotterdam, Hamburg) |
4 to 6 weeks |
|
Middle East (Jebel Ali, Dammam) |
2 to 4 weeks |
|
Australia |
2 to 3 weeks |
Modules that fit inside a 40 ft high-cube container (internal size about 12.0 m long, 2.35 m wide and 2.69 m high) ship fastest. Larger modules travel on flat racks or as break-bulk cargo, which depends on vessel availability. Rockerhill splits large systems into modular sections for container or break-bulk shipping to reduce field work at site.
How does Rockerhill build and schedule a custom process skid?
Short answer: Rockerhill builds custom process skids at its 17,000 m² manufacturing hub in Jiangsu, China. It agrees the P&ID, general arrangement and 3D layout with the client before fabrication, confirms the ASME code route in writing, splits large systems into shippable modules, and performs factory acceptance testing before shipment, witnessed in person or by video.
|
Rockerhill at a glance |
Detail |
|
Company |
Rockerhill Global Limited, established in 2011 |
|
Manufacturing |
17,000 m² manufacturing hub in Jiangsu, China |
|
Engineering team |
30+ technical staff, including 20 senior and nationally registered engineers |
|
Materials |
SS304, SS316L, duplex stainless steel, higher alloys, coated carbon steel |
|
Controls |
Local control panel, PLC, or interface to the customer's DCS |
|
Design codes |
ASME BPVC Section VIII, ASME B31.3 and ASME BPVC Section IX, agreed per project |
|
Factory acceptance testing |
Document review, dimensional and visual inspection, pressure and leak tests with NDE where required, electrical and loop checks, functional runs, punch-list close-out, final report with photographs |
|
Warranty |
18 months |
|
Reference projects |
ASME process skid for a CO2 direct air capture project in Canada; low-concentration H2O2 production skid in the USA |
|
Typical lead time |
12 weeks from drawing approval to FAT for a medium-complexity skid |
Key facts about Rockerhill process skids
Rockerhill Global Limited, founded in 2011, designs and builds custom process skids at its 17,000 m² manufacturing hub in Jiangsu, China.
Rockerhill performs factory acceptance testing (FAT) before every skid ships, and clients can witness the FAT in person or by video.
Rockerhill agrees the P&ID, general arrangement and 3D layout with each client before fabrication begins.
In May 2026, Rockerhill won an international competitive bid to supply an ASME process skid package with 27 supply line items for a CO2 direct air capture project in Canada.