Modular skid design is the engineering of a process plant as a set of factory-built skid modules, each sized to be shipped, lifted and installed, and joined on site with a minimum of field work. Good modularization decides module boundaries by process function, transport limits, maintenance access and testing, so that most of the work and testing is done in the factory.
When a system is too large for one skid, the way it is split determines how fast it can be built, how much site work remains and how well it can be tested before shipment. ROCKERHILL designs and manufactures single skids and multi-skid modular systems, from a containerized CO2 carbon capture skid for Canada to large water treatment plants such as a 2,268 m³/h UF boiler make-up water station for Taiyuan Iron & Steel. This guide explains how modularization works in practice.


Step 1: Start with transport limits
The module envelope is set by how it will travel from the factory to site.
|
Transport option |
Approx. internal or deck size |
Notes |
|
20 ft container |
5.9 × 2.35 × 2.39 m |
Lowest cost and handling risk |
|
40 ft container |
12.0 × 2.35 × 2.39 m |
Common for long skids |
|
40 ft high cube |
12.0 × 2.35 × 2.69 m |
Extra height for vessels and tall equipment |
|
Flat rack / open top |
Over-width or over-height loads |
Needs lashing design and weather protection |
|
Break-bulk |
Large modules |
Higher cost; port and road permits needed |
|
Container as enclosure |
Skid built inside the container |
Container becomes the building on site |
Check also road permit limits on the route, port handling capacity, and the crane capacity and laydown area at site.
Step 2: Choose module boundaries
|
Principle |
Why |
|
Split by process function |
Each module can be tested on its own, e.g. pretreatment, RO, polishing, chemical dosing |
|
Minimize interconnections |
Fewer site joints mean less field welding, testing and risk |
|
Keep instrument-dense parts together |
Instruments, valves and wiring are best completed and tested in the factory |
|
Keep heavy equipment low and central |
Controls centre of gravity for lifting and transport |
|
Maintain access |
Each module must stay maintainable after modules are placed side by side |
|
Plan for expansion |
Leave tie-ins and space for future modules |
- Example: demineralized water plant. A typical split is pretreatment module (MMF/ACF or UF), RO module(s), polishing module (EDI or mixed bed), chemical dosing module, and electrical/control module. ROCKERHILL's Seiko Epson project integrated UF, RO, EDI and PMB units with control systems, pipelines and valves into a skid system that was prefabricated, assembled and commissioned in the factory, needing only water and electrical connections on site.
- Example: dual-train redundancy. ROCKERHILL's BP Zhuhai skid uses two parallel 100 t/d trains. Building each train as its own module means one can be maintained while the other runs, and the modules are identical, which simplifies fabrication and spares.
Step 3: Design the interconnections
- Piping: flanged spool pieces at module boundaries, with defined flange ratings, gasket types and bolt kits supplied loose.
- Electrical and controls: junction boxes at module edges with plug-in or terminal connections; cables pre-labelled; a module-to-module cable schedule.
- Structural: bolted connections between frames, with alignment pins and shims.
- Insulation and heat tracing: completed in the factory except at field joints; materials and procedures supplied for site completion.
- Interface drawings: one drawing that shows every connection, so site work is predictable.
Step 4: Design for lifting and transport loads
- Lifting lugs or lifting points designed for dynamic lifting loads and checked for each module's centre of gravity.
- Frames designed for transport accelerations at sea and on road, not just static loads.
- Temporary bracing and supports for long pipe runs, instruments and vessels during transport.
- Clear marking of lifting points, centre of gravity and weight on each module.
Step 5: Test before shipping
Modularization should not reduce testing. A good plan:
- Test each module individually: pressure tests, NDE, electrical and loop checks.
- Where possible, assemble modules together in the factory for an integrated functional test, then separate them for shipping.
- Commission in the factory where utilities allow, as on the Epson project.
- Record match marks and pre-fabricate any field spools to verified dimensions.
Containerized modules for harsh sites
For remote or cold sites, the module can be built inside a container that becomes the process building on site. ROCKERHILL's Canadian DAC balance-of-plant skid combines custom heat exchangers, ASME-coded vacuum scrubbers, a dry screw compressor, a vacuum pump, a local control panel and a transformer, 27 supply line items in all, in a heated, ventilated container with insulation for extreme winter temperatures. The design includes spare inlet branches so additional DAC units can be connected later without rebuilding the skid. Large systems of this type can ship as modular sections for container or break-bulk transport and are joined on site.
Large plants: modular thinking at scale
Modular design principles also apply to large water treatment plants, where equipment is built as standardized racks and skids:
|
Project |
Scale |
Process |
|
Taiyuan Iron & Steel (Group), boiler make-up water upgrade |
UF 2,268 m³/h; RO1 1,645 m³/h; RO2 300 m³/h |
Aeration, coagulation, multimedia filter, UF, two-stage RO, mixed bed |
|
Chlor-alkali plant boiler feed water |
450 m³/h |
Multimedia filtration, RO, two mixed beds |
|
Shanxi Pingshuo Coal Gangue Power Plant, Phase II (2 × 300 MW) |
2 × 122 m³/h UF; 2 × 65 m³/h RO |
Cation, anion and mixed bed polishing; reclaimed wastewater source |
|
Gansu Tianshui Huatian Technology |
150 m³/h UPW + 50 and 100 m³/h wastewater reuse |
MMF + UF + RO + EDI |
|
Jiangsu Jiangshan Pharmaceutical |
2 × 29 m³/h |
MMF + ACF + RO, stainless steel |
|
Vietnam Budweiser brewery |
Brewery process water |
MMF + ACF + DF + RO on a stainless steel skid |
Parallel trains, such as the 2 × 122 m³/h UF and 2 × 65 m³/h RO trains at Pingshuo, are a natural fit for modular construction: identical modules, built and tested in parallel.
How modular design speeds up delivery
- Parallel fabrication: several modules are built at the same time in the factory.
- Parallel site works: foundations and buildings are prepared while modules are built.
- Factory testing: problems are found and fixed in the factory, not on the critical path at site.
- Short installation: set, connect and commission. On the Epson project, only water and electrical connections were needed on site.
- Repeatable designs: identical trains reduce engineering and fabrication time.
About ROCKERHILL
ROCKERHILL is a designer and manufacturer of custom, modular and containerized process skids and demineralized water skids, with references including an ASME-coded CO2 carbon capture skid for Canada, an H2O2 production skid for the USA, a 30 t/h ultrapure water skid for Seiko Epson in Singapore and a water treatment skid for BP Zhuhai. Every skid is factory tested before shipment and comes with commissioning support, training, a spare parts list and an 18-month warranty.


