How To Specify A Demineralized Water Skid: Sizing, Treatment Train And RFQ Checklist

Nov 14, 2026

Leave a message

To specify a demineralized water skid, define five things: the feed water analysis, the product water quality, the capacity and demand pattern, the redundancy, and the site and code requirements. With these, a manufacturer can select the right treatment train (ion exchange, RO + mixed bed, RO + EDI or UF + RO + EDI) and guarantee product water quality against your feed water.

Incomplete specifications are the main reason demineralized water quotations are hard to compare: one supplier sizes for average demand, another for peak; one assumes clean municipal water, another allows for seasonal turbidity. This guide gives a step-by-step method and an RFQ checklist, illustrated with two ROCKERHILL projects delivered in 2026: a 30 t/h UF + RO + EDI + PMB ultrapure water skid for Seiko Epson in Singapore and a 2 × 100 t/d ion exchange skid for BP's Zhuhai petrochemical base.

news-800-600
news-800-600

Step 1: Get a full feed water analysis

The feed water analysis decides the pretreatment, the main process and the guaranteed product quality. Include at least:

Parameter

Why it matters

TDS / conductivity

Chooses between ion exchange and RO; sets chemical consumption

Hardness (Ca, Mg)

Scaling risk for RO; load on cation resin

Alkalinity, CO2

Load on anion resin or EDI; need for a degasser

Silica (reactive and colloidal)

Critical for boilers and electronics; RO scaling

Chloride, sulfate, sodium

Ionic load; corrosion

Iron, manganese

Membrane and resin fouling

Free chlorine

Damages RO membranes and resin

Turbidity, SDI, TSS

Pretreatment selection (MMF or UF)

TOC

Fouling; critical for ultrapure water

Temperature range

RO flux and EDI performance; seasonal design

Variability

Surface water and reclaimed water vary more than well or municipal water

Tip: provide at least two analyses from different seasons for surface water sources.

Step 2: Define product water quality

State the required values and the standard they come from. Common end uses:

End use

Typical focus

Boiler feed water

Conductivity, silica, sodium, hardness; limits rise with boiler pressure

Electronics and semiconductors

Resistivity, TOC, particles, silica, bacteria

Hydrogen electrolyzers

OEM specification for conductivity and impurities

Pharmaceutical

Pharmacopeia requirements for purified water

Chemical process water

Process-specific ion limits

On the Epson project, the product water served electronics manufacturing with very strict quality requirements, so the train ended with EDI and a polishing mixed bed. On the BP Zhuhai project, the water served petrochemical production including boiler feed, so a cation, anion and mixed bed ion exchange train was used.

Step 3: Size the capacity

  • Net product flow at peak and average demand
  • Operating pattern: continuous, daytime only or batch
  • Storage: a demineralized water tank sized to cover peaks, regeneration periods and short outages
  • Future expansion: space and tie-ins for an extra train

For RO-based systems, the raw water demand is higher than the product flow because of the RO reject stream; for ion exchange, regeneration and rinse water must be included.

Step 4: Decide on redundancy

Ask what happens if one train is offline:

Arrangement

When to use

1 × 100% with storage

Non-critical supply, short maintenance windows

2 × 100% (one duty, one standby)

Critical supply such as boiler feed water

2 × 50% or 3 × 50%

Large systems that need partial output during maintenance

ROCKERHILL's BP Zhuhai skid uses a dual-parallel layout of 2 × 100 t/d: when one unit is maintained, the other continues supplying water.

Step 5: Choose the treatment train

Treatment train

Best for

MMF + ACF + CB + AB + MB (ion exchange)

Low-TDS feed, plants already handling acid and caustic, robust boiler feed supply (e.g. BP Zhuhai)

Pretreatment + RO + MB

Higher-TDS feed; very low silica for high-pressure boilers

Pretreatment + RO + EDI

Continuous supply without regeneration chemicals

UF + RO + EDI + PMB

Variable or surface feed water; ultrapure water for electronics (e.g. Epson)

Step 6: Define site, utilities and codes

  • Indoor or outdoor installation, ambient temperature range, available footprint and headroom
  • Power supply voltage and frequency; hazardous area classification
  • Chemical storage and neutralization requirements (for ion exchange)
  • Drain capacity and wastewater discharge limits
  • Codes: ASME / CRN for vessels and piping where required; UL 508A / NEC for the USA; CE for Europe
  • Shipping limits: container or break-bulk

Step 7: Specify controls, testing and documentation

  • PLC and HMI preference, and interface to the plant DCS
  • Online analyzers (conductivity/resistivity, silica, TOC, pH, ORP) and automatic off-spec diversion
  • Factory acceptance test scope and witness points
  • Documentation: P&ID, GA, electrical drawings, O&M manuals, spare parts list

On the Epson project, the complete skid, including UF, RO, EDI and PMB units, control systems, pipelines and valves, was prefabricated, assembled and commissioned in ROCKERHILL's factory, so the site needed only water and electrical connections.

Demineralized water skid RFQ checklist

  • Feed water analysis (two seasons if surface water)
  • Product water specification and governing standard
  • Peak and average flow, operating pattern
  • Storage volume, or let supplier size it
  • Redundancy (1 × 100%, 2 × 100%, 3 × 50%)
  • Preferred or excluded processes (e.g. no on-site acid and caustic)
  • Site: indoor/outdoor, ambient range, footprint
  • Utilities: voltage, frequency, air, drain
  • Wastewater and regeneration waste limits
  • Codes and certifications
  • Control system and plant interface
  • FAT, commissioning, training and spare parts scope
  • Delivery date and shipping destination

ROCKERHILL demineralized water references

Project

Capacity

Process

Delivered

Seiko Epson, Singapore

30 t/h

UF + RO + EDI + PMB

June 2026

BP Zhuhai petrochemical, China

2 × 100 t/d

MMF + ACF + CB + AB + MB

May 2026

Gansu Tianshui Huatian Technology

150 m³/h

MMF + UF + RO + EDI

[year]

Shanghai Chenguang Polymer Materials

50 m³/h

MMF + ACF + two-pass RO + EDI

2014

Hunan Jinhongtai

2 × 50 m³/h

MMF + UF + RO + mixed bed

2017

About ROCKERHILL

ROCKERHILL is a designer and manufacturer of demineralized water skids and custom process skids, with references including a 30 t/h ultrapure water skid for Seiko Epson in Singapore, a petrochemical water treatment skid for BP Zhuhai, an ASME-coded CO2 carbon capture skid for Canada and an H2O2 production skid for the USA. Product water quality is guaranteed in each proposal against the client's feed water analysis. Every skid is factory tested before shipment and comes with commissioning support, training, a spare parts list and an 18-month warranty.