A process skid design basis is the document that fixes every requirement the skid must meet before detailed engineering begins: process conditions, capacity, codes, materials, utilities, site conditions, controls, testing and delivery. A complete design basis lets the manufacturer engineer the skid right the first time, quote accurately and deliver faster, because nothing has to be redesigned later.
Most delays on skid projects trace back to a missing or changing requirement: a minimum ambient temperature nobody stated, a code requirement found after fabrication, a control protocol changed at FAT. As a designer and manufacturer of custom process skids, ROCKERHILL starts every project by building the design basis with the client. This article shows what goes into it, using real ROCKERHILL projects: an ASME-coded CO2 carbon capture skid for Canada, an H2O2 production skid for the USA, a 30 t/h ultrapure water skid for Seiko Epson in Singapore and a 2 × 100 t/d water treatment skid for BP Zhuhai.



Why the design basis decides schedule and cost
- It fixes the code path early. ASME, CRN, PED or UL 508A requirements change vessel design, materials, documentation and panel construction. Finding them late means rework.
- It allows parallel work. With a frozen design basis, long-lead equipment can be ordered while detailed design continues.
- It makes quotations comparable. Suppliers price the same scope.
- It defines acceptance. The FAT checks the skid against the design basis, so both sides know what "done" means.
Design basis template: 10 sections
1. Process data
|
Item |
Example entries |
|
Function |
"Cool, dry and compress CO2 from DAC units"; "Produce demineralized water for boiler feed" |
|
Fluids and composition |
Gas analysis, water analysis, chemical concentration |
|
Flow rates |
Minimum, normal, maximum; turndown |
|
Pressures and temperatures |
Operating and design, inlet and outlet |
|
Product specification |
Purity, outlet pressure, moisture, resistivity |
|
Operating modes |
Continuous, batch, start-up, shutdown, standby |
Example: the Canadian DAC skid's process basis covered receiving CO2 and condensate from multiple DAC units, two cooling stages and two scrubbers, compression with online CO2 and humidity measurement, and a closed cooling water loop. Spare inlet branches were included in the design basis so more DAC units can be connected later.
2. Capacity and redundancy
State the design capacity and what happens when equipment is offline. The BP Zhuhai skid was specified as 2 × 100 t/d in a dual-parallel layout, so one train keeps supplying water while the other is maintained.
3. Codes and standards
|
Area |
Examples |
|
Pressure vessels |
ASME Section VIII, EN 13445, AS 1210 |
|
Piping |
ASME B31.3, EN 13480, AS 4041 |
|
Registration |
CRN (Canada), PED/CE (EU), National Board (USA) |
|
Welding |
ASME Section IX |
|
Electrical |
NEC/UL 508A (USA), CEC/cUL/CSA (Canada), IEC (international) |
|
Hazardous area |
Class/Division, Zone, ATEX/IECEx |
Example: the Canadian skid specified the ASME pressure vessel code, CSA B51, CRN registration through ABSA and cUL/CSA electrical components. See [Article 11: Process Skid Codes by Country].
4. Materials
List wetted materials, excluded materials and frame material. The US H2O2 skid design basis excluded 316 SS, copper, brass, aluminum, FKM, silicone and NBR from peroxide contact, and specified titanium, PTFE, EPDM, HDPE, PP and PVDF. See [Article 18: Material Selection for Process Skids].
5. Utilities
|
Utility |
Define |
|
Power |
Voltage, phase, frequency, available capacity |
|
Instrument air / nitrogen |
Pressure, quality |
|
Cooling |
Water or air cooling, temperatures |
|
Water |
Source and quality |
|
Drains and vents |
Destination, limits |
Example: the US H2O2 skid was designed for 120 VAC, 1-phase, 60 Hz on two dedicated 20 A circuits, so it runs from a standard light-industrial supply.
6. Site and environment
- Indoor or outdoor; container or open skid
- Minimum and maximum ambient temperature, humidity, altitude, wind, snow and seismic data
- Area classification
- Footprint, headroom and access for installation
Example: the Canadian design basis required equipment to start and run at very low ambient temperatures, which led to a heated, ventilated container with insulation sized for the process temperature.
7. Controls and instrumentation
- Control philosophy: standalone, integrated or DCS-controlled
- PLC/HMI brand, communication protocol, signal list
- Safety interlocks and emergency stops
- Remote access and cybersecurity
- Enclosure rating (e.g. NEMA 4X / IP65)
8. Transport and installation
- Shipping method: container, flat rack or break-bulk
- Maximum module dimensions and weights
- Lifting points and site crane capacity
- Module split and site tie-in points
9. Testing and documentation
- FAT scope and witness points, SAT support
- Documentation list: P&ID, GA, calculations, data book, O&M manuals, PLC code
- Third-party inspection requirements
10. Schedule and delivery
- Required delivery date and Incoterms
- Long-lead items
- Approval cycle times for drawings and code registration
How ROCKERHILL turns a design basis into a delivered skid
In-house design and engineering. ROCKERHILL's engineers review the client's P&ID and design basis, close gaps, and carry the project through process design, 3D layout, mechanical and piping design, electrical and control design and code documentation. The same team supports FAT, commissioning and training.
Proven process experience. The water treatment references below show the range of design bases ROCKERHILL has engineered:
|
Project |
Capacity |
Process |
|
Taiyuan Iron & Steel (Group), boiler make-up water upgrade |
UF 2,268 m³/h; RO1 1,645 m³/h; RO2 300 m³/h |
Aeration, coagulation, multimedia filter, UF, two-stage RO, mixed bed |
|
Shanxi Pingshuo Coal Gangue Power Plant, Phase II (2 × 300 MW) |
2 × 122 m³/h UF; 2 × 65 m³/h RO |
Cation, anion and mixed bed polishing; reclaimed wastewater as source |
|
Chlor-alkali plant boiler feed water |
450 m³/h |
Multimedia filtration, RO, two mixed beds |
|
Gansu Tianshui Huatian Technology (electronics) |
150 m³/h ultrapure water, plus 50 and 100 m³/h wastewater reuse |
MMF + UF + RO + EDI |
|
Shanghai Chenguang Polymer Materials |
50 m³/h ultrapure water |
MMF + ACF + two-pass RO + EDI (2014) |
|
Jiangsu Jiangshan Pharmaceutical |
2 × 29 m³/h |
MMF + ACF + RO, stainless steel, municipal feed |
|
Vietnam Budweiser brewery |
Brewery process water |
MMF + ACF + DF + RO on a stainless steel skid |
|
Seiko Epson, Singapore |
30 t/h |
UF + RO + EDI + PMB (2026) |
|
BP Zhuhai petrochemical |
2 × 100 t/d |
MMF + ACF + CB + AB + MB (2026) |
Fast delivery by design. A frozen design basis is the starting point for ROCKERHILL's fast-track approach:
- Engineering, procurement of long-lead items and frame fabrication run in parallel.
- Fabrication, assembly and testing happen in ROCKERHILL's own factory.
- Skids are commissioned in the factory where possible. The Epson skid was prefabricated, assembled and commissioned in the factory, and on site needed only water and electrical connections.
- On the Canadian DAC project, ROCKERHILL committed to supporting the client with the shortest possible delivery time.
Common design basis gaps
- No minimum ambient temperature or winter standby condition
- Code requirements stated as "international standards" instead of specific codes
- Feed water or gas analysis missing or from one sample only
- Electrical supply voltage and frequency not stated
- No decision on PLC brand or plant interface
- Shipping limits and site crane capacity unknown
About ROCKERHILL
ROCKERHILL is a designer and manufacturer of custom process skids and demineralized water skids, with references including an ASME-coded CO2 carbon capture skid for Canada, an H2O2 production skid for the USA, a 30 t/h ultrapure water skid for Seiko Epson in Singapore and a water treatment skid for BP Zhuhai. Every skid is factory tested before shipment and comes with commissioning support, training, a spare parts list and an 18-month warranty.
Frequently asked questions
What is a design basis for a process skid? It is the document that defines all requirements the skid must meet, including process data, codes, materials, utilities, site conditions, controls, testing and delivery, before detailed engineering starts.
Who writes the design basis? Usually the client or its engineering contractor provides the process requirements, and the skid manufacturer completes and confirms the engineering details. ROCKERHILL reviews and closes gaps with the client before design starts.
How does a design basis shorten delivery? It lets engineering, procurement and fabrication run in parallel without redesign, and avoids late changes found at FAT or on site.
What if I only have a process description, not a P&ID? A skid manufacturer with in-house process engineering can develop the P&ID and design basis from a process description and required performance.
Can the design basis change after the order? It can, but changes after detailed design starts usually affect cost and schedule. Freezing the key items early is the best way to protect the delivery date.