How To Size A Bar Screen: Channel Width, Flow, Velocity And Head Loss

Nov 27, 2026

Leave a message

 

Sizing a bar screen means choosing the number of screen channels, the channel width and depth, and the rack length so that the screen passes the peak flow at a safe velocity, keeps grit moving at low flow and stays within the head loss the channel walls can hold. Get it right and the screen runs quietly for decades. Get it wrong and the channel overtops in a storm, grit fills the channel in dry weather or rags are forced through the bars.

This guide sets out the full sizing sequence in eight steps, with a worked example for a three-channel inlet works. It deliberately does not repeat the head loss equations, which are covered in detail in our bar screen head loss calculation article. Here we put those equations in context, alongside the decisions that come before and after them. It is the same sequence ROCKERHILL engineers follow when we size a multi-rake bar screen for a client's channel.

The eight steps at a glance

Step

Decision

Main inputs

What it protects against

1

Design flows

Minimum, average and peak flow; future growth

Undersized or oversized screens

2

Bar spacing

Downstream equipment, process

Debris passing, excessive screenings

3

Number of channels

Peak flow, redundancy policy, maintenance

Loss of screening during maintenance

4

Water depth

Downstream hydraulics, upstream sewer level

Wrong velocities, surcharging upstream

5

Channel width

Peak flow per channel, through-bar velocity, open-area ratio

Rags forced through, high head loss

6

Low-flow check

Minimum flow, approach velocity

Grit settling in front of the rack

7

Head loss and wall height

Blinding allowance, freeboard

Overtopping in storms

8

Rack length and discharge

Channel depth, floor level, discharge height, angle

Screenings handling and access problems

Step 1: Fix the design flows

A bar screen is sized on three flows, not one.

Flow

Used for

Peak flow (peak wet weather flow for sewage, maximum intake flow for raw water)

Channel width, through-bar velocity, head loss and wall height

Average flow

Normal operating cycle, screenings volume, energy use

Minimum flow (night-time dry weather flow, minimum intake demand)

Approach velocity check, so grit does not settle

For municipal wastewater, peak wet weather flow is often two to four times the average dry weather flow, and more in combined sewer catchments. Use the figure in the design basis, and size for the design horizon, typically 20 years or more, because widening a concrete channel later costs far more than a slightly wider screen today. Where a plant will be extended in phases, it is often better to build all channels now and install screens in them as the flow grows.

Step 2: Choose the bar spacing

The bar spacing sets the open-area ratio of the rack, which drives everything in Step 5. Choose it from what you are protecting downstream: 10 to 25 mm for most municipal inlet works, 3 to 10 mm for fine screening, and 25 to 50 mm for pumping stations, stormwater and intakes. Our bar spacing and 2D vs 3D screening guide explains the choice in detail.

The open-area ratio of a bar rack is:

Open-area ratio = b / (b + w)

where b is the clear spacing and w is the bar thickness facing the flow.

Clear spacing b

Typical bar thickness w

Open-area ratio

6 mm

5 mm

0.55

10 mm

8 mm

0.56

15 mm

10 mm

0.60

25 mm

10 mm

0.71

50 mm

12 mm

0.81

Bar thickness is a structural choice as well as a hydraulic one. Thinner bars give more open area, but they must still resist the full differential head of a blinded rack without bending.

Step 3: Decide the number of channels

Most design standards and good practice call for at least two mechanically cleaned screens, so the plant can keep screening while one is maintained. A common arrangement is:

Arrangement

When it is used

1 mechanical screen + 1 bypass channel with a manual rack

Small plants and pumping stations

2 duty screens, each sized for 50 to 100% of peak flow

Medium plants

N duty + 1 standby (for example 2 + 1)

Larger plants and where screening is critical, such as ahead of an MBR

Each channel needs a way to isolate it upstream and downstream, normally penstocks or stoplogs. Isolation is not just for maintenance: closing a channel at low flow is the simplest way to keep the approach velocity up, as the worked example shows.

Step 4: Set the water depth

The water depth at the screen is rarely a free choice. It is fixed by the hydraulics of the plant: the level of the incoming sewer or intake, the level control downstream (a weir, a flume or the pump wet well) and the head loss of everything in between. Work the hydraulic profile backwards from the downstream control to find the depth at the screen at minimum, average and peak flow.

If the depth at peak flow is very large, the channel can be narrower. If the upstream sewer must not surcharge, the head loss allowance in Step 7 may become the controlling constraint.

Step 5: Calculate the channel width

With the peak flow per channel, the water depth and the open-area ratio, the width follows from the target through-bar velocity. For mechanically cleaned bar screens, the velocity through the clear openings at peak flow is usually kept between 0.6 and 1.0 m/s, with 0.9 m/s a common design maximum.

Effective rack width = Q / (V × d × r)

Symbol

Meaning

Q

Peak flow per channel (m³/s)

V

Target through-bar velocity (m/s)

d

Water depth at peak flow (m)

r

Open-area ratio, b / (b + w)

The channel itself must be a little wider than the effective rack width, because the side frames and seals of the screen take up space. Ask the supplier for the exact allowance for their design.

Quick reference: effective rack width needed per 1 m³/s of flow, per 1 m of water depth, at V = 0.9 m/s

Bar spacing / bar thickness

Rack width per m³/s per m depth

6 mm / 5 mm

2.04 m

10 mm / 8 mm

2.00 m

15 mm / 10 mm

1.85 m

25 mm / 10 mm

1.56 m

50 mm / 12 mm

1.38 m

For example, 0.5 m³/s at 1.25 m depth through a 15 mm rack needs about 1.85 × 0.5 / 1.25 = 0.74 m of effective rack width. These figures use the vertical water depth, which is slightly conservative because an inclined rack is longer than the depth.

Step 6: Check the approach velocity at low flow

A channel sized for the storm is often too slow in the middle of the night. If the velocity in the channel just upstream of the screen falls below about 0.4 m/s, grit and sand settle in front of the rack, build up a bank, and eventually jam the rake at the bottom of its travel.

Approach velocity v = Q / (W × d)

using the full channel width W and the actual water depth at that flow. If the check fails, the usual fixes are:

Close one or more channels at low flow so the remaining screen carries more flow.

Raise the downstream level control less at low flow, or use a flume whose level falls with flow.

Narrow the channel with a benching or fillets at the invert.

As a last resort, accept the settling and provide flushing or easy cleaning access.

At peak flow, the approach velocity should not be much above about 0.9 m/s, or debris is pressed hard onto the rack.

Step 7: Allow for head loss and set the wall height

A clean rack loses only a few tens of millimetres. A rack partly covered with screenings loses many times more, and the channel must hold that higher upstream level at peak flow. Calculate the head loss with the rack clean and at your chosen blinding allowance, typically 30 to 50%, using the orifice equation set out in our head loss calculation guide.

Then set the channel wall height:

Wall height ≥ peak water depth + design head loss + freeboard

with a freeboard of at least about 0.3 m, or as the local standard requires. Add a high-level alarm and, where the upstream sewer cannot surcharge, an emergency overflow or bypass. The control system should start the rakes on rising differential level well before the design head loss is reached. Our article on why bar screens clog explains what happens when it does not.

Step 8: Fix the rack length, angle and discharge height

The last step sizes the screen itself. The rack must reach from the channel invert to a discharge point high enough for the screenings chute to feed a conveyor, washer compactor or container.

Screen length along the rack ≈ (channel depth + discharge height above floor) / sin θ

Item

Typical value

Installation angle θ

60° to 80° for mechanically cleaned screens (75° typical)

Discharge height above floor

Set by the conveyor, compactor or skip; often 0.8 to 1.5 m

Floor openings and access

Allow space to lift out rakes and drive, and a lifting point above

A steeper angle shortens the footprint and the rack, but screenings are more likely to fall back from the rake. A flatter angle is gentler on the screenings but needs a longer screen and more floor space.

Worked example: a three-channel inlet works

Design data (illustrative only):

Input

Value

Peak flow

1.2 m³/s

Minimum night flow

0.25 m³/s

Arrangement

3 channels, 2 duty + 1 standby, each sized for 0.6 m³/s

Water depth at peak flow

1.2 m

Water depth at minimum flow

0.5 m

Bar spacing / thickness

6 mm / 5 mm (open-area ratio 0.545)

Target through-bar velocity at peak

≤ 0.9 m/s

Channel depth (invert to floor)

2.5 m

Discharge height above floor

1.0 m

Angle

75°

Step 5, width. Effective rack width = 0.6 / (0.9 × 1.2 × 0.545) = 1.02 m. Allowing for the side frames, choose a 1,200 mm channel with an effective rack width of about 1,100 mm. Check: clear width = 1.10 × 0.545 = 0.60 m; clear area = 0.60 × 1.2 = 0.72 m²; through-bar velocity = 0.6 / 0.72 = 0.83 m/s. Within the limit.

Step 6, low flow. At minimum flow with both duty channels open, each carries 0.125 m³/s: v = 0.125 / (1.2 × 0.5) = 0.21 m/s. Too slow; grit will settle. With one channel closed by its penstock, the duty screen carries 0.25 m³/s: v = 0.25 / (1.2 × 0.5) = 0.42 m/s. Acceptable. The control philosophy should therefore close a channel automatically below a set flow.

Step 7, head loss. Approach velocity at peak = 0.6 / (1.2 × 1.2) = 0.42 m/s. Using the orifice equation from our head loss article, the clean rack loses about 0.04 m. At 30% blinding the through-bar velocity rises to about 1.19 m/s and the loss to about 0.11 m; at 50% blinding it reaches about 0.22 m. Allow 0.3 m for head loss plus 0.3 m freeboard: the wall must stand at least 1.2 + 0.3 + 0.3 = 1.8 m above the invert, which the 2.5 m deep channel easily provides. (This simple check ignores the rise in upstream depth as the rack blinds, which slightly lowers the velocity. It is conservative.)

Step 8, rack length. (2.5 + 1.0) / sin 75° = 3.5 / 0.966 = about 3.6 m along the rack.

Result: three 1,200 mm wide multi-rake bar screens at 6 mm spacing, 75°, about 3.6 m long, two duty and one standby, with motorised penstocks to switch channels at low flow and differential level control. With fine 6 mm spacing and a continuous municipal load, a multi-rake screen rather than a climber is the natural fit (see multi-rake vs climber screen).

Don't forget the screenings

Sizing the channel is not the end. The screenings must go somewhere, and their volume grows quickly as the spacing gets finer. Indicative screenings volumes for municipal sewage, before washing and compaction, are:

Bar spacing

Indicative screenings volume

25 mm

about 5 to 15 L per 1,000 m³

12 mm

about 15 to 35 L per 1,000 m³

6 mm

about 30 to 60 L per 1,000 m³

3 mm

about 50 to 100 L per 1,000 m³

These ranges vary widely with the catchment, the sewer system and the season, and storm first flushes can bring several times the daily average in an hour. Use local data where it exists. Size the conveyor and washer compactor for the storm peak, not the average day.

Information to send for a sizing check

Minimum, average and peak flow, now and at the design horizon

Channel width, depth and invert level, or the proposed hydraulic profile

Water depth at the screen at minimum and peak flow

Required bar spacing, or the downstream equipment it must protect

Number of channels and redundancy policy

Floor level, discharge height and screenings handling (conveyor, compactor, skip)

Water type (municipal, industrial, seawater) and temperature range

Power supply, control requirements and the local design standards

Design, engineering and in-house manufacturing

ROCKERHILL does the sizing calculation and builds the screen, so the screen in your channel is the screen that was calculated.

Capability

What it means for your project

Hydraulic check before proposal

We check width, velocities at minimum and peak flow, head loss and wall height from your data before we offer a screen, and tell you if the channel needs to change.

Customisation

Every screen is built to the channel: widths up to 4,800 mm, depths of about 7.3 m, bar spacing 3 to 50 mm, a choice of bar profiles, and AISI 304, 316L, duplex 2205 or coated carbon steel.

Structural design

Bars, frame and rakes are designed for the differential head of a blinded rack and for the rake loads, with calculations issued for approval.

Project documentation

General arrangement drawings, data sheets, calculations, ITPs, O&M manuals and spare parts lists, issued for approval before fabrication.

Codes and standards

ASTM, ASME, EN and GB codes or the project specification; welding to ASME Section IX; EN 10204 3.1 material certificates.

In-house manufacturing and testing

Fabricated, pickled and passivated in our own workshops in China, then fully assembled and run in the factory before shipment. Third-party inspection is welcome.

Complete channel package

Screens, penstocks and stoplogs for channel isolation, and screenings handling equipment, from one engineering team.

Global project references

ROCKERHILL has sized and built screens and channel equipment for projects in 30 countries.

Frequently asked questions

How do you size a bar screen? Fix the minimum and peak flows, choose the bar spacing and number of channels, set the water depth from the hydraulic profile, calculate the width from the peak flow and a through-bar velocity of 0.6 to 1.0 m/s, check the approach velocity at low flow, and check head loss and wall height.

How do you calculate bar screen channel width? Effective rack width = Q / (V × d × r), where Q is peak flow per channel, V the through-bar velocity, d the water depth and r the open-area ratio b / (b + w). Add the supplier's allowance for side frames.

What is the recommended approach velocity for a bar screen? At least about 0.4 m/s at low flow to keep grit moving, and not much above about 0.9 m/s at peak flow.

What is the maximum velocity through a bar screen? For mechanically cleaned screens, usually 0.9 to 1.0 m/s through the clear openings at peak flow.

How many bar screens do I need? At least two mechanically cleaned screens, or one screen plus a bypass with a manual rack, so screening continues during maintenance. Larger plants often use N duty plus one standby.

What head loss should I allow for a bar screen? Calculate it for a partly blinded rack, typically 30 to 50% blinded. Many channels are designed for 150 to 600 mm. See our head loss calculation.

How long is a bar screen? Roughly (channel depth + discharge height above floor) / sin θ. A 2.5 m deep channel with a 1.0 m discharge at 75° needs a screen about 3.6 m long.

What happens if a bar screen channel is too wide? The approach velocity falls at low flow, grit settles in front of the rack and jams the rake. Closing a channel at low flow is the usual fix.

Can ROCKERHILL size the screen for me? Yes. Send your flows and channel drawing and our engineers will return a hydraulic check and a sized screen proposal.


Want your channel checked? Send your design flows, hydraulic profile and channel drawing to ROCKERHILL. Our engineers will check the velocities and head loss and return a sized bar screen proposal. Contact Allie at Allie.s@rockerhillcn.com.